Chinook Sweet Memorial Rehabilitation, Chinook MT, WR2500103
Posted
Sep 30, 2026
Oct 15, 2026
Site clearing, grubbing and removals of stumps and existing playground surfacing. Erosion control, site protection and permitting. 172 CY embankment/fill - imported. Preparation of playground container, including subgrade preparation, 125 LF concrete edge restraint, and coordination with already-contracted playground installer. 232 SY 6" concrete sidewalk. Concrete ramp, concrete stairs and 53 LF tubular steel handrails. Underground storm utilities, including manhole structure, pump, and drain pipe. Electrical utilities, including service panel upgrade, area light, and electrical service for light and pump. Landscaping, including 2,315 SY seeding, topsoil preparation, and maintenance. Underground irrigation system. Traffic control and all miscellaneous work necessary therefore and incidental thereto.