Description: Work includes 2,146 CY earthwork excavation (mag 205); 1,348 CY surplus material (mag 205); 1,331 SY subgrade preparation (mag 301), 8" scarify and recompact; 407 SY subgrade preparation (mag 301), 6" under curb, sidewalk, and ramps; 238 ton 3" ac, mag 3/4" mix, single lift (mag 321); 222 CY abc, 6" pavement section (mag 310 & 702-1); 45 CY abc, 4" under curb, sidewalk, and ramps (mag 310 & 702-1); 3,378 SF sidewalk and ramps (mag 340); 554 sf 3' valley gutter (mag 340); 559 LF 6" single curb, mag 222, (mag 340); 4 EA curb and gutter transition, qcsd 221q (mag 340). See attached file.
City · AZ, US
Solicitation files and supporting documents for this bid.
Decision makers connected to this RFP from Town of Chino Valley.
Adjacent opportunities open for bidding right now.
CountyFL
Posted
Oct 12, 2026
Nov 12, 2026
Work includes 406 SY 5" thick reinforced concrete sidewalk or slab w/ sub-base - bleacher pads, sidewalks; 77 sy 6" thick reinforced concrete pavement with sub-base - drive apron; 3 EA detectable warning surface; 2,200 LF galvanized chain link fence - 8.0' height 6-gauge galvanized chain link fence, posts, footings, fasteners, etc; 2 EA single swing gate - 8.0' height x 4' wide 6-gauge galvanized chain link gate, latch hardware, posts, footings, fasteners, etc. ; 1 ea double swing gate - 8.0' height x 8' wide (two 4' panels) 6-gauge galvanized chain link gates, latch hardware, posts, footings, fasteners, etc. See attached file.
CityCA
Posted
Oct 14, 2026
Nov 4, 2026
The project includes the following work: installation of a 24" tie-in with a blind flange and thrust block on the existing 36" wastewater influent pipeline and backfilling the excavation. Procurement and delivery of one 24" eccentric plug valve and one 36-inch eccentric plug valve to the project site. Installation of a shoring box, a 1" steel plate bolted to the outside of channel, and a galvanized chain link fencing inside the channel, and a 1" a36 steel plate and hydrophilic waterstop.
CityIL
Posted
Oct 8, 2026
Nov 5, 2026
Project consists of dredging approx. 3,643 CY of sediment, installing approx. 733 LF of steel sheet piling and 463 LF (approx. 575 SY) of geobag shoreline protection. All dredged material will be reused on site as ill behind the sheet piling and within the geobag shoreline stabilization system. The project also includes installation of a ishing pier, fountain, and aeration system for the pond.
CityWA
Posted
Sep 18, 2026
Oct 21, 2026
Project consists of constructing a new UV disinfection system, two pump stations and buildings, a 50 mg lined lagoon, irrigation pivots, chlorination system, dechlorination system, two creek crossings, diesel generators, over 1,000' of yard piping ranging in size from 4" to 30" diameter, controls upgrades and electrical upgrades.